More than seven years after the Grenfell Tower fire, the inquiry has published its final report, outlining the root causes of the fire.
Introducing the 14-part report, Inquiry Chair Sir Martin Moore-Bick said that all of the 72 deaths resulting from the Grenfell Tower fire were “avoidable” and that the residents of Grenfell Tower had been “badly failed over a number of years”.
An executive summary of the Inquiry states that “the fire at Grenfell Tower was the culmination of decades of failure by central government and other bodies in positions of responsibility in the construction industry to look carefully into the danger of incorporating combustible materials into the external walls of high-rise residential buildings and to act on the information available to them.”
Watch the Video
Key Takeaways from the Grenfell Tower Inquiry Final Report
The Government Missed Opportunities to Identify Risks
The report suggests that the government at the time failed to identify risks posed by the use of combustible cladding panels and insulation in high-rise buildings. The Department for Communities and Local Government was “well aware” of the risks but did not heed warnings correctly, particularly after a Environment and Transport Select Committee in December 1999 raised the danger of certain external cladding systems.
The government is also responsible for not removing external wall panel benchmarks (Class 0) that were not fit for purpose, despite being made aware of the danger on several occasions.
Between 2012 and 201, major cladding fires as a result of polymeric insulation and aluminium composite panels with unmodified polyethylene cores were also brought to the department’s attention numerous times.
The Building Research Establishment Failed to Warn the Government on Dangers
The Building Research Establishment’s (BRE) testing of the fire safety of external walls was described as being “marred by unprofessional conduct, inadequate practices, a lack of effective oversight, poor reporting and a lack of scientific rigour.” This meant that key information about fire safety testing was not drawn to the government’s attention.
BRE’s reports into previous major fires were deemed “far from comprehensive” and gave the government the false impression that the regulations and guidance were working effectively.
Dishonesty of Manufacturers
Companies that manufactured and sold cladding panels and insulation products were found to have deliberately manipulated testing processes, misrepresenting data and misleading the market. Arconic Architectural Products, who manufactured and sold the Reynobond 55 PE rainscreen panels used in the external walls of Grenfell Tower, deliberately concealed the danger of using these highly flammable products. Arconic Architectural Products was fully aware by late 2007 that the panels performed badly in fires, but continued to allow customers in the UK to purchase it, despite a fire-resistant version being available.
The manufacturers of the foam insulation used at Grenfell are also at fault. Celotex manufactured combustible polyisocyanurate foam insulation which was then tested in accordance with BS 8414 in May 2014. The test was found to be incomplete and misleading, and the fact that it passed the BS 8414 test meant that Celotex could market the insulation as “acceptable for use in buildings above 18 metres in height”, despite BS 8414 being wholly unsuitable for classifying individual products.
The National House Building Council Gave in to Commercial Pressures
The National House Building Council was found to have been complicit in a culture of not wanting to “upset its own customers” by revealing the scale of the use of combustible insulation in the external walls of high-rise buildings. The report found that the pressure of commercial interests prevented the body from being “essentially regulatory.”
Grenfell’s Fire Assessor was “Ill-Qualified” for the Role
The fire assessor responsible for Grenfell Tower “drifted” into their role without being subject to a formal procurement process. They were found to misrepresent their experience and qualifications and were not qualified to carry out fire risk assessments on buildings of the size and complexity of Grenfell Tower.
Rainscreen Panels Were Chosen Due to Budget Restrictions
The aluminium composite material (ACM), Reynobond 55 PE, was specified in the Grenfell Tower refurbishment largely due to cost, as the project has exceeded its budget significantly. Rydon, the principal contractor, was able to offer a substantial saving through the use of ACM panels as a result of its relationship with its intended cladding sub-contractor, Harley.
Ineffective Management and Leadership of the London Fire Brigade
The report reveals significant shortcomings in the London Fire Brigade’s response, including a failure to respond effectively to the high number of phone calls seeking help from both within and outside the building. The control room was underprepared for the volume of calls, and there was a lack of training in handling fire survival guidance calls.
The Royal Borough of Kensington and Chelsea Demonstrated a “Marked Lack of Respect for Human Decency and Dignity”
The Royal Borough of Kensington and Chelsea’s response to the fire was “inadequate” as it did not have effective plans to deal with the mass displacement of a large number of people from their homes. Many Muslim residents felt that there was no consideration that Ramadan was being observed at the time and that there was “no regard for their cultural and religious needs.”
Statutory Guidance Was Poorly Worded
The system of regulating the construction and refurbishment of high-rise residential buildings was found to be “seriously defective”. Approved Document B was described as “misleading”, “poorly worded” and written in such a way that it appeared to designers that compliance with its terms also meant compliance with building regulations.
Building Control Officer Competence Deadline Extended by HSE
Building control professionals in England have received a 13-week extension to allow them more time to complete competence assessments.
The Director of Building Safety...
Fire Brigades Union Criticises Guidelines on Evacuating High-Rise Buildings
A new document from the Home Office which outlines new evacuation strategies from high-rise residential buildings has been described as “too little….too...
Facilities managers in 2024 face a spectrum of challenges, requiring a strategic and proactive approach to risk management.
John Greenough, FM Sector...
Advanced Supports ‘Be Ready Campaign’ for Building Safety
Fire protection solutions manufacturer Advanced is supporting the new Building Safety Regulator’s "Be Ready" campaign, which calls on the industry to...
Financial statements published by the Grenfell Inquiry show that its total expenditure is at £170 million.
Total expenditure for the period 01 April 2022 to 31...
Procurement consortium LHC is asking fire safety experts to get involved in the new Fire Safety (FS2) Framework.
FS2 covers the end-to-end spectrum of fire safety...
IWFM Calls on FMs to Update Fire Safety Knowledge for 2023
IWFM and PlanRadar have released a newly updated fire safety management good practice guide for its members.
The document covers the changes to fire safety from 23...
The much-discussed Building Safety Bill has received Royal Assent and will become an Act of Parliament.
The bill has been one of the most talked-about legislative...
The Cuba Street Development – A 570ft Skyscraper With One Staircase?
An application for a residential 51-storey tower close to London’s Canary Wharf has been delayed due to fire safety strategy concerns from the London Fire...
Government Says Developers Must Pay to Fix Cladding Crisis
House building firms have until March 2022 to remediate unsafe cladding on 11-18 metre buildings.
The Secretary of State for Levelling Up, Michael Gove, is warning the...
Southern Based Gym Group Converts To Rinnai's Low-GWP ASHP To Support Decarbonisation Programme
A chain of gyms has successfully piloted Rinnai’s LOW-GWP commercial ASHP (Air Source Heat Pump) with the aim of replacing their existing carbon intensive electric storage water heater systems which rely on multiple electrical immersions. Click Image To Read More
Rinnai Hybrid Heat Pump System Provides Practical, Economic, And Technical Solution At Luxury Complex In The City Of London
Rinnai Low-GWP 50kW Heat Pump, bespoke thermal stores, Plate Heat Exchangers and ten cascaded I2HY20 Hydrogen- ready continuous flow water heaters specified at new development in the heart of Farringdon district of London. Click Image To Read More
Energy Transition Update
Huge construction projects funded by extensive financial credit will assist in replacing fossil fuels with green renewables and alternative energies. Click Image To Read More
New Government Prioritises Clean & Cost-Effective Power
Chris Goggin observes and comments on the priorities of the new Energy Secretary Ed Miliband. Enhancing renewable energy production is a key objective of the current government, as is the creation of a publicly owned Energy company that safeguards UK customers from external cost elevations. Additional insights into large solar and wind projects as well as information on further home heating plans will also be shared. Click Image To Read More
Misinformation on New Direction Of UK Energy Policy – More Of The Same But Different.…
North Sea exploration licenses have been the subject of much media attention of what is and is not the new Government’s policy. Chris Goggin of Rinnai tries to unravel the thread from the needle... Click Image To Read More
Energy Transition Update
Large scale construction projects, financial deals worth billions and cross-continental cooperation between big businesses aggregates towards an active international clean energy transition. Click Image To Read More
2024 Winner Announced
The only award recognising the front of house receptionists in the Corporate sector. Click Image To Read More
Data Is Power In Planning
Are you maximising the planning power of data when training your people, and demonstrating compliance? Click Image To Read More
Guest Contributor – Dan Teare
Read exclusive insights from Dan Teare, Founder of DJT Partners & subject matter expert on IoT monitoring solutions, software implementations, and bespoke mobile applications. Click Image To Read More
Meet The Team
FM Qualifications at the College of Central London
Qualifications are essential to gaining recognition and respect. Our mission is to provide skills and knowledge to help you achieve success in IWFM level 5 and 6. Click Image To Read More